    ACA Report against Gamuda on Sabah Road

    RM 3.156 million/km for some upgrading, bridges and drainage work without bituminuos surfacing. Hmmm, not a bad deal.

    Someone must have made a lot of money here.

    For comparison, in 1982 the construction of an international expressway from Seremban to Air Hitam cost RM 3.95 million/km. That's for a 4-lane dual carriageway with the earthworks platform widened to allow for a future 3rd lane. Of course, we have to allow for inflation and higher operating costs in Sabah.


    Construction New Road Project From Sapulut to Kalabakan, Sabah

    To:

    The Director / Officer In-Charge
    Anti-Corruption Agency (ACA)
    Tawau

    Dear Sir,

    Re: AN ACA REPORT – Request for Investigation of Any Corrupt Practices and Abuse of Power on the Construction of ‘Jalan Sapulut – Kalabakan, Tawau, Sabah’ as a Design & Build Contract at the Contract Sum of RM565 million

    I, DATUK KONG HONG MING (NRIC NO.530306-12-5323), a Malaysian of Lot 21, 3rd Floor, Block C, Damai Point, Luyang, Kota Kinabalu (Hand-phone 0138888188 and 088-23355 hereby make this report calling upon ACA to investigate any corrupt practices or abuse of power committed in the implementation of a road construction project by the Federal Government through Jabatan Kerja Raya.

    The subject matter of this complaint is a Design & Build contract for a road project described as ‘Jalan Sapulut – Kalabakan, Tawau’ at the contract sum of RM565 million. The design for the road project at the contract sum of RM565 Million for 179 kilometer was a permanent bituminous road with sealed pavement.

    The contractual obligations of the contractor in a Design & Build contract require the contractor to provide the design, scope of work and specifications to be approved by the Government and to build according to the approved design, scope of work and specifications. Thereafter, based on negotiation between the Government and the contractor, the Government awarded the Design & Build contract at the negotiated contract sum, in this case, RM565 million for 179 kilometer of sealed road with bituminous pavement.

    In a Design & Build contract like this contract, the contractor is not permitted to amend or vary the design and scope of work. In a nutshell, the contractor must complete the contract in full conformity with the approved design and scope of work without variation order.

    The Project was completed sometime in early 2008 and the contractor has demobilized from the site recently.

    Unfortunately, instead of building 179 kilometer of bituminous pavement serving as a major truck road linking the south and north of the State of Sabah, the Government has only completed only a 179 kilometer of standard gravel road wholly contrary to the Design & Build contract for a bituminous sealed road.

    Before the Design & Build contract, the existing road was already then a good gravel road built and used by timber operator for logging activities.

    I also urge your ACA experts to investigate into the very sub-standard and extremely poor quality of work done and workmanship carried out in this mega project costing our Malaysians taxpayers some RM565 million. It is just too plain and obvious in inspecting the newly completed retaining structures and concrete roadside drains which are already now in such deplorable conditions.

    It is a crime to allow such shoddy workmanship and inferior work in this expensive project. What was the basis for the Government to accept the road as practically and satisfactorily completed?

    This is a case of an outrageous and scandalous wrongdoing. It is more than just a serious wastage and abuse of public funds. It has also deprived all Malaysians especially Sabahans in Tawau a good system of road network in furtherance of our social and economic development.

    Those who were responsible for the suffering of the people must be held accountable for this tragic loss of public funds and blatant abuse of power.

    It will be more outrageous for us, especially the ACA, to ignore it.

    Thank you for your attention and further necessary actions against those culprits who were responsible for any corrupt practices and abuse of power.

    Yours faithfully,


    __________________________
    DATUK KONG HONG MING
    Dated: 3rd July 2008

    ************************************************** *************

    11th August 2008

    To:

    The Director

    Anti-Corruption Agency (ACA)

    Kota Kinabalu


    Dear Madam,

    Re: AN ACA REPORT – Request for Investigation of Any Corrupt Practices and Abuse of Power on the Construction of ‘Jalan Sapulut – Kalabakan, Tawau, Sabah’ as a Design & Build Contract at the Contract Sum of RM565 million

    I, KONG HONG MING (NRIC NO.530306-12-5323), a Malaysian of Lot 21, 3rd Floor, Block C, Damai Point, Luyang, Kota Kinabalu (Hand-phone 0138888188 and 088-23355 hereby make this report calling upon ACA to investigate any corrupt practices or abuse of power committed in the implementation of a road construction project by the Federal Government through Jabatan Kerja Raya.

    On 03.07.2008, I lodged this complaint at the ACA office in Tawau. I provided some documents for the purpose of investigation. However, I am uncertain whether any investigation has been carried out. I must congratulate you that your ACA officers in Tawau were courteous and professional to complainant at least to me during two occasions. But, I was surprised that in another occasion while I was there, a male staff was not so happy to accept my report on other matter.

    The subject matter of this complaint is a Design & Build contract for a road project described as ‘Jalan Sapulut – Kalabakan, Tawau’ at the contract sum of RM565 Million. The design for the road project at the contract sum of RM565 Million for 179 kilometer was a permanent bituminous road with sealed pavement.

    The contractual obligations of the contractor in a Design & Build contract require the contractor to provide the design, scope of work and specifications to be approved by the Government and to build according to the approved design, scope of work and specifications. Thereafter, based on negotiation between the Government and the contractor, the Government awarded the Design & Build contract at the negotiated contract sum, in this case, RM565 million for 179 kilometer of sealed road with bituminous pavement.

    In a Design & Build contract like this contract, the contractor is not permitted to amend or vary the design and scope of work. In a nutshell, the contractor must complete the contract in full conformity with the approved design and scope of work without variation order.

    The Project was completed sometime in early 2008 and the contractor has demobilized from the site recently.

    Unfortunately, instead of building 179 kilometer of bituminous pavement serving as a major truck road linking the south and north of the State of Sabah, the Government has only completed only a 179 kilometer of standard gravel road wholly contrary to the Design & Build contract for a bituminous road.

    Before the Design & Build contract, the existing road was already then a good gravel road built and used by timber operator for logging activities.

    I also urge your ACA experts to investigate into the very sub-standard and extremely poor quality of work done and workmanship carried out in this mega project costing our Malaysians taxpayers some RM565 million. It is just too plain and obvious in inspecting the newly completed retaining structures and concrete roadside drains which are already now in such deplorable conditions.

    It is a crime to allow such shoddy workmanship and inferior work in this expensive project. What was the basis for the Government to accept the road as practically and satisfactorily completed?

    This is a case of an outrageous and scandalous wrongdoing. It is more than just a serious wastage and abuse of public funds. It has also deprived all Malaysians especially Sabahans in Tawau a good system of road network in furtherance of our social and economic development.

    Those who were responsible for the suffering of the people must be held accountable for this tragic loss of public funds and blatant abuse of power.

    It will be more outrageous for us, especially the ACA, to ignore it.

    Thank you for your attention and further necessary actions.

    Yours faithfully,


    __________________________

    DATUK KONG HONG MING

    My Address: Lot 21, 3rd Floor, Block C, Damai Point, Luyang, Off Jalan Damai, Kota Kinabalu

    Tel (Office) 088-233558, Fax 088-245646, Hand-phone 0138888188

    http://mt.m2day.org/2008/content/view/17858/84/

    Actual construction by Irama Duta: http://www.iramaduta.net.my/project.html
    py

  2. #2
    Join Date
    Oct 2008
    Posts
    13,391

    RM563mil on Sabah Road does not include asphaltic paving

    RM563mil spent on 'gravel road' in Sabah

    Mar 9, 09 10:55am

    Those in Sabah’s construction circles have reacted with surprise to Works Minister Mohd Zin Mohamed’s statement that a RM536 million 'highway' to Tawau had all along been envisaged as a gravel road.

    More…
    py

Visitors found this page by searching for:

gamuda sabah

gamuda project in sabah

gamuda-irama duta

gamuda sabah project hiway

gamuda sabah project

powered by vBulletin aca code of ethics

gamuda at sabah

development of road design standard in sabah

aca sabah politician

contractor road works in sabah

contractor for new road project

gamuda corruption

road constractor in sabah

road contractors in sabah

road design and build contract

paving road contractors in sabah

DATUK KONG HONG MING PROFILE

SEO Blog

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •